Phase 5 sprinkler upgrades at centre:mk – Eagle & Field Walk

Value:

£3,180,000

Duration:

48 weeks

Client:

Hermes CMK General Partner Ltd

Completed:

September 2019

Following the successful completion of the previous four phases, phase five of the sprinkler replacement works focussed on the Eagle and Field Walk areas of the centre which lie either side of the events area, Middleton Hall.

The project involved the replacement of the existing sprinkler system and associated life safety systems on Eagle and Field Walk as well as to the back of house areas and plant rooms surrounding this area of the mall.

The existing ‘dry’ pipework was replaced like for like with a ‘wet’ system with additional pipework added to correctly zone Landlord area protection. The project also included installation of new fire detection, PAVA, emergency lighting system, cable containment and lighting busbar.

All sprinkler pipework from the previous installation to various shop unit zone control valves were replaced including replacement/installation of 16 new control valve sets that serve the mall of Eagle and Field Walk, back of house and Tenant and other Landlord areas.

The project also included:
The installation of trace heating and lagging in all unheated/back of house spaces, as well as throughout the mall areas.
The Testing and review of the isolation valve monitoring system, which are within the tenant’s demise.
An environmental clean of all plant rooms.

Where possible lights within the mall were re-used or re-lamped rather than being fully replaced and the installation also included features to make future works more straight forward. For example the containment installed above the ceiling has space for additional cabling and access hatches were created every 6m within the ceiling to provide convenient access for future works or maintenance.