Unit 200, Lakeside Centre Ltd, Landlord Enabling Works

Value:

£2.1 million

Duration:

16 weeks

Client:

Completed:

October 2024

Overview
The Unit 200 project at Lakeside Centre Ltd involved a complex package of landlord-enabling works aimed at modernising and enhancing the functionality of the retail space. This high-profile project required precise engineering, structural modifications, and compliance with fire safety standards to accommodate future tenant requirements and improve the overall shopping experience.

The 16-week program, with a contract value of approximately £2.1 million, demanded a multidisciplinary approach to deliver structural adaptations and high-quality installations within the bustling retail environment of Lakeside Shopping Centre.

Scope of Work

Structural Modifications for Rooflights 
Alterations to existing structural steelwork to facilitate the installation of two large glazed rooflight systems. 
Construction and installation of a bespoke support framework to ensure the rooflights’ stability and integration into the existing structure.

Rooflight Installation
Installation of two glazed rooflight systems to enhance natural lighting within the retail space. 

Concrete Slab Adjustments
Formation of openings in the concrete slab directly beneath the rooflights to create visual and spatial connectivity between the upper mall and the floors below.

Escalator Service Pits
Construction of double escalator service pits to accommodate new vertical transportation systems, ensuring seamless movement between floors.

Service Risers
Installation of structural steelwork to create service risers at the upper mall and roof levels, followed by the removal of the concrete slab for integration with the wider building systems.

Fire Safety Compliance 
Fireproof encasement of structural steelwork to meet regulatory requirements and ensure long-term safety and durability.

Summary

The Unit 200 project showcased expertise in structural engineering, precision planning, and effective project management within a live retail environment. The enabling works not only addressed the technical challenges of modifying existing structures but also prioritised minimal disruption to Lakeside’s ongoing operations. 

The successful completion of this 16-week project has laid the groundwork for future developments within the unit, providing an upgraded infrastructure that enhances tenant options and improves the shopping experience for visitors. Delivered on time and within budget, the project is a testament to effective collaboration, skilled execution, and commitment to excellence.