Building Services Archives | Princebuild Ltd

  • Project: Phase 3 sprinkler upgrades at centre:mk
    Value: £1,200,000
    Duration: 20 weeks
    Client: Hermes Plc
    Completed: April 2018
  • Project: Creation of Pathology Lab, Charing Cross Hospital
    Value: £170,000
    Duration: 5 weeks
    Client: Imperial College Healthcare NHS Trust
    Completed: June 2017
    Charing Cross Hospital
  • Project: Deer Walk Guest Services Lounge centre:mk
    Value: £5,800,000
    Duration: 44 weeks
    Client: Hermes CMK General Partner Ltd
    Completed: June 2017
  • Project: Cassio Metro Leisure Centre, fire damage repairs
    Value: £830,000
    Duration: 36 weeks
    Client: Arun Associates
    Completed: May 2017
    Caasio Metro Centre pool
  • Project: Office Refurbishment, Sol House, Northampton
    Value: £1,000,000
    Duration: 16 weeks
    Client: Workman LLP / Simply Business
    Completed: October 2016
    Office Refurbishment Sol House
  • Project: Conversion of flats into classrooms
    Value: £42,000
    Duration: 5 weeks
    Client: The Priory Group
    Completed: September 2016
    classroom conversion
  • Project: Essential refrigeration works & Fresh Look, Morrisons Northampton
    Value: £1,300,000
    Duration: 10 weeks
    Client: Wm Morrison Supermarkets
    Completed: September 2016
    Morrisons Northampton
  • Project: Reigate Beaumont Care Home Refurbishment
    Value: £160,000
    Duration: 10 weeks
    Client: Barchester Healthcare
    Completed: May 2016
    Reigate Beaumont Care Home Refurbishment
  • Project: Extension & Refurbishment of Care Home
    Value: £630,000
    Duration: 32 weeks
    Client: Together for Mental Wellbeing
    Completed: February 2016
    Bexhill Care Home
    View Case Study
  • Project: New Store Fit-out, Morrisons, Colindale
    Value: £4,000,000
    Duration: 14 weeks
    Client: Wm Morrison Supermarkets
    Completed: March 2016
    Morrisons Colindale
    View Case Study
  • Project: Construction of Chinnor Community Building
    Value: £1,200,000
    Duration: 46 weeks
    Client: Chinnor Parish Council
    Completed: February 2016
    Chinnor Community Pavillion
  • Project: Conversion of Two Flats to Living Accomodation
    Value: £160,000
    Duration: 12 weeks
    Client: Danshell
    Completed: February 2016
    Conversion of Two Flats to Living Accomodation at Thors Park for Danshell
  • Project: Major Alterations Work to Live Jewson Store
    Value: £750,000
    Duration: 21 weeks
    Client: Jewson Saint-Gobain Ltd
    Completed: October 2015
    Jewson Hereford
  • Project: Jack Hunt School, Life Cycle Works
    Value: £327,000
    Duration: 5 weeks
    Client: Bouygues UK
    Completed: September 2015
    Jack Hunt School, Life Cycle Works
  • Project: Smiths Nissan Showroom Refurbishment
    Value: £200,000
    Duration: 12 weeks
    Client: Smiths Motor Group
    Completed: September 2015
    Smiths Motor Group Peterborough
  • Project: Internal Refurbishment of Donington Church Hall
    Value: £40,000
    Duration: 9 weeks
    Client: Donington Church PCC
    Completed: March 2015
    Donington Church Hall
  • Project: Office Refurbishment, Chelmsford
    Value: £160,000
    Duration: 6 weeks
    Client: Threadneedle UK Property Trust
    Completed: February 2015
    Threadneedle UK Property Trust Chelmsford
  • Project: Newlands Shopping Centre Lighting & Ceiling Refit
    Value: £400,000
    Duration: 16 weeks
    Client: Ellandi
    Completed: November 2013
    shopping centre lighting
  • Project: New Hyundai Retail Outlet for Smith Motor Group
    Value: £560,000
    Duration: 32 weeks
    Client: Smiths Motor Group
    Completed: August 2013
    New Hyundai Retail Outlet for Smiths Motors
  • Project: Remodelling of Offices, W M Morrison, Swan Valley
    Value: £470,000
    Duration: 16 weeks
    Client: W M Morrison
    Completed: May 2013
    Swan Valley